Archive for the ‘Minutes’ Category

h1

Meeting Minutes for 4/24/08

April 24, 2008

Date: 4/24/08
Time: 2:00pm – 3:30pm
Present: Myles, Chris, Victor
Recorder: Chris

This is a general update for what we have been doing thus far. Most of our time has been spent on implementing App-Trac. Myles worked on the models and controls. Victor worked on the database control. Chris worked on the view (interface). After the model view and control was complete, we combined the three together and debugged issues that arose. We are currently in the final steps of the implementation process and will be complete in time for our presentation this coming Tuesday, 4/29/08.

h1

Meeting Minutes for 2/18/08

February 18, 2008

Date: 2/18/2008

Time: 9:15pm – 10:30pm

Team Leader: Victor Sklutovsky

Recorder: Myles Garvey

Members Present: Victor Sklutovsky, Chris Padilla, Myles Garvey

Summary: Merged SRS Document and wrote use cases.

Action Items:

  • Padilla will finish his section based on new notes and ideas discussed.
  • Garvey will finish his section based on new notes and ideas discussed.
  • Sklutovsky doing presentation and merging SRS Deliverable 2.
h1

2/14/08 Meeting Minutes

February 16, 2008

Date: 2/14/2008

Time: 2:30pm – 3:30pm

Team Leader: Victor Sklutovsky

Recorder: Myles Garvey

Members Present: Victor Sklutovsky, Chris Padilla, Myles Garvey

Summary: Discussed new ideas and edited SRS document.

Action Items:

  • Padilla worked on SRS document update.
  • Garvey discussed and recorded new ideas with Sklutovsky.
  • Sklutovsky discussed new ideas with Garvey and worked on cases.
  • All are editing SRS document, implementing new ideas and adding requirements for deliverable 2.
h1

2/7/2008 Meeting Minutes

February 7, 2008

Date: 2/7/2008
Time: 2:30pm – 3:30pm
Team Leader: Victor Sklutovsky
Recorder: Myles Garvey
Members Present: Victor Sklutovsky, Chris Padilla, Myles Garvey

Summary: Continued to work on sections of the document and discuss any new ideas.

Action Items (did not change since last meeting):

  • Padilla will work on section 1 (Introduction) of the SRS document.
  • Garvey will work on section 2 (General Description) of the SRS document.
  • Sklutovsky will work on section 3 (Specific Requirements) of the SRS document.
  • Progress will be shown during our regular meeting time, Thursdays from 2:30-3:30.
  • Finished project will be uploaded to site before Monday’s class time. Specific deadline will be set at Thursday’s meeting.
h1

2/5/2008 Meeting Minutes

February 6, 2008

Date: 2/5/2008
Time: 3:30pm – 4:45pm
Team Leader: Victor Sklutovsky
Recorder: Chris Padilla
Members Present: Victor Sklutovsky, Chris Padilla, Myles Garvey

Summary: We discussed and created our log web site (http://d3group.wordpress.com). Furthermore, we developed a SRS template and split up the work load into three sections for the SRS document that is due 2/11/2008.

Action Items:

  • Padilla will work on section 2 (Introduction) of the SRS document.
  • Garvey will work on section 3 (General Description) of the SRS document.
  • Sklutovsky will work on section 4 (Specific Requirements) of the SRS document.
  • Progress will be shown during our regular meeting time, Thursdays from 2:30-3:30.
  • Finished project will be uploaded to site before Monday’s class time. Specific deadline will be set at Thursday’s meeting.
Follow